How much concrete do I need? Slabs, footings and posts

By Christos Papandreou. Updated . About 11 minutes to read.

Working out how much concrete a job needs is a volume calculation, and the geometry is easy: a slab is a box and a post hole is a cylinder. The arithmetic goes wrong elsewhere. Plans mix feet with inches and metres with millimetres. Ready-mix is sold by the cubic metre or the cubic yard, and premix bags are sold by weight. Concrete is lost to spillage and uneven ground, and a short pour costs far more than a little left over.

This guide covers the volume of each common shape and how to keep the units straight. It explains the waste allowance and how many bags of each size make a given volume, and when bags stop making sense. It also gives the weight of what you are about to place, with two worked examples, a slab and a set of fence posts, run through the site's calculators. The method gives quantities only. How thick a slab must be, what strength of concrete to use and what reinforcement it needs is a design question for the local building code or an engineer.

Volume of each shape

Every formula below gives the net volume, the concrete that ends up in the finished shape. Waste is added afterwards.

Slab, patio, driveway or floor

V = L × W × t × n

L and W are the length and width, t the thickness and n the number of identical slabs. Split an L-shaped slab into two rectangles and add them. The concrete slab calculator takes this shape.

Strip footing under walls

V = L_c × B × D
L_c = 2 × (a + b) − 4 × B   for a rectangle of outside size a × b

B is the footing width and D the depth of concrete. Measure the length along the centreline of the footing, not around the outside. At each corner the two outside lengths overlap by one footing width, so the outside perimeter counts each corner block twice.

Pad footings under posts or columns

V = n × L × B × D

Both footing types are in the concrete footing calculator.

Round column, pier or tube form

V = n × π × D² ÷ 4 × H

D is the diameter and H the height. A 12 in tube form holds 0.785 ft³ per foot of height.

Post hole

V = n × (π × D² ÷ 4 − A_post) × (h − h_gravel)
A_post = s² for a square post,  π × s² ÷ 4 for a round one

The post takes up part of the hole, and a layer of gravel at the bottom takes up more. Use the actual post size, not the nominal one: a 4 × 4 is 3.5 in square and a 6 × 6 is 5.5 in. A square post fits in a round hole only if the hole is wider than the post's diagonal. The column and post hole calculator checks this and handles both shapes.

Handling the units

Most volume errors come from mixed units. The rule is to convert every dimension to one length unit before you multiply, then convert the volume at the end.

Between the two systems:

VolumeCubic feetCubic yardsCubic metres
1 ft³10.037040.02832
1 yd³2710.7646
1 m³35.311.3081

A cubic metre is about 30 % more than a cubic yard. A quote in one and an order in the other is a common way to end up a truck short. The volume converter handles any other pair.

The waste allowance

The net volume is what the drawing shows. What you need to buy is more, because:

The calculators apply waste as a straight percentage of the net volume:

V_order = V × (1 + waste)

They default to 10 %. For slabs, 5 % suits well-formed work on a level, compacted base and 10 % suits uneven ground or a first pour. Footings poured against earth need 10 % or more, and rough trenches more again. The weight output uses the net volume, because waste does not end up in the structure.

Premix bags: how much one bag makes

Bagged premix is sold by dry weight. The site's calculators use the yield printed on US premix concrete bags, 0.60 ft³ of fresh concrete per 80 lb bag (QUIKRETE Concrete Mix product data). That is 0.0075 ft³ per pound of dry mix, and the same yield per kilogram is applied to the other sizes:

BagYieldBags per yd³Bags per m³
80 lb0.60 ft³ (17.0 L)4558.9
60 lb0.45 ft³ (12.7 L)6078.5
50 lb0.375 ft³ (10.6 L)7294.2
40 lb0.30 ft³ (8.5 L)90117.7
30 kg0.496 ft³ (14.0 L)54.471.2
25 kg0.413 ft³ (11.7 L)65.385.4
20 kg0.331 ft³ (9.4 L)81.6106.8
bags = V_order ÷ yield of one bag, rounded up

The metric yields are scaled from the US figure by weight. Your brand may differ, so check the label. Mortar, sand mix, high-strength, fast-setting and lightweight products all yield different volumes. Use the yield printed on their bag. The concrete bag calculator converts any volume into bags of every size at once.

When bags stop making sense

One cubic yard is 45 bags of 80 lb: 3600 lb of dry mix to lift, carry and mix by hand. That is why every concrete calculator on the site warns once the order passes one cubic yard. Above that, ready-mix delivered by truck is usually cheaper, faster and more uniform, because a large pour mixed batch by batch is hard to finish before the first batches start to stiffen. Bags remain the sensible choice for post holes, small pads, steps and repairs, and where a truck cannot reach. Enter your local prices in the calculators to compare the two costs.

The weight of the concrete

The calculators take normal-weight concrete at 2400 kg/m³, about 150 lb/ft³ (EN 1991-1-1, Table A.1). That is 2.4 tonnes per cubic metre. A 4 in slab weighs about 50 lb per square foot. The figure matters for a suspended slab, for a trailer or a small truck carrying a load, and for what a crew can handle in a day. The weight of dry bags is a separate figure: 45 bags of 80 lb weigh 3600 lb before any water is added. Other materials are listed in the density of materials reference.

Worked example: a shed base slab

A shed base is 20 ft by 12 ft. The drawing gives a thickness of 5 in. You allow 10 % for waste and compare 80 lb bags with ready-mix.

  1. Thickness in feet: 5 ÷ 12 = 0.4167 ft.
  2. Area: 20 × 12 = 240 ft².
  3. Net volume: 240 × 0.4167 = 100.0 ft³, which is 100.0 ÷ 27 = 3.70 yd³ (2.83 m³).
  4. With 10 % waste: 100.0 × 1.10 = 110.0 ft³, or 4.07 yd³ (3.11 m³).
  5. In 80 lb bags: 110.0 ÷ 0.60 = 183.3, so 184 bags. In 60 lb bags it would be 245, and in 25 kg bags 267.
  6. Weight in place: 2.83 m³ × 2400 kg/m³ = 6796 kg, about 14 980 lb, or 6.8 tonnes.

The concrete slab calculator reproduces these figures with 20 ft, 12 ft, 5 in, one slab and 10 % waste. It also warns that the order is more than one cubic yard. At 184 bags this is a ready-mix job. Ready-mix is usually ordered in steps of a quarter or half yard, so you would order 4.25 yd³ rather than 4.07.

The same slab in metric: a base of 6 m by 4 m at 100 mm is 6 × 4 × 0.1 = 2.40 m³, 2.64 m³ with 10 % waste, or 226 bags of 25 kg.

Worked example: a run of fence posts

A fence needs twelve 4 × 4 posts. Each is set in a 12 in round hole, 36 in deep, on 6 in of gravel for drainage. Allow 10 % waste and use 80 lb bags.

  1. Hole area: π × 1.0² ÷ 4 = 0.7854 ft² (12 in = 1.0 ft).
  2. Post area: 3.5 × 3.5 ÷ 144 = 0.0851 ft². Net area of concrete: 0.7854 − 0.0851 = 0.7003 ft².
  3. Concrete depth, above the gravel: 36 − 6 = 30 in = 2.5 ft.
  4. Concrete per hole: 0.7003 × 2.5 = 1.751 ft³, which is 1.751 ÷ 0.60 = 2.92 bags of 80 lb.
  5. Twelve holes: 12 × 1.751 = 21.01 ft³. With 10 % waste: 23.11 ft³ (0.86 yd³).
  6. Bags: 23.11 ÷ 0.60 = 38.5, so buy 39 bags of 80 lb, or 62 bags of 50 lb.

The column and post hole calculator gives the same result for these inputs: post holes, 12 in diameter, 36 in deep, square 3.5 in post, 6 in gravel, 12 holes, 10 % waste. At under one cubic yard, bags make sense here. Round up per hole when you mix: a hole needing 2.92 bags will not be finished with the last bag split across two holes. Pour the extra into the holes that were dug wider than the rest.

For round columns or tube forms, choose the column option. Six 12 in tubes 4 ft high hold 3.14 ft³ each, 18.85 ft³ in all, and 35 bags of 80 lb with 10 % waste.

Ordering tips

Sub-base, excavation and reinforcement

The concrete is only part of the material list. Each of these has its own calculator:

The size of a footing comes from the load it carries and the bearing capacity of the soil. Its depth comes from the local frost line. The footing size and soil bearing capacity calculators show how that is done. The design of any footing, slab or reinforcement that carries a building still comes from the local code or an engineer, not from a quantity estimate.

Common mistakes

Limits of the method

The formulas assume straight-sided shapes of uniform section: rectangular slabs and footings with level bases, and straight cylinders for holes and columns. Bells at the base of piers, stepped footings, stem walls and sloping slabs add volume the formulas do not include. Work those out separately or raise the waste allowance. Bag yields are those of standard premix concrete. The weight assumes normal-weight concrete at 2400 kg/m³ and counts only the concrete. The calculators estimate quantities, not adequacy. The thickness, strength grade and reinforcement of anything structural come from the building code that applies where you build, or from an engineer's design.

Calculators used in this guide

Results are estimates. They do not replace the governing code, class or flag requirements, or a check by a competent person. Report an error in this guide

By Christos Papandreou. How the numbers are checked.