Civil engineering formulas
The formulas behind the 30 civil calculators, on one page you can print or save as a PDF. Each block lists its variables and standard; the heading opens the calculator, with its assumptions and a worked example.
Concrete and masonry
Brick calculator: bricks and mortar for a wall
Bricks:
bricks per area = 1 / ((L + j) × (H + j))
bricks = A_net × bricks per area × wythes × (1 + waste)
Mortar, the method of BIA Technical Note 10:
mortar per brick = ((L + j) × (H + j) − L × H) × W
collar joint = A_net × j (double wythe only)
- L, H, W — specified length, height and width of the brick
- j — mortar joint thickness, ⅜ in in the US and 10 mm in metric brickwork
- A_net — wall area less doors and windows
- wythes — one or two thicknesses of brick
| Brick | Size, in | Bricks per ft² with ⅜ in joints |
|---|---|---|
| Modular | 7⅝ × 2¼ × 3⅝ | 6.86 |
| Standard | 8 × 2¼ × 3⅝ | 6.55 |
| Queen | 7⅝ × 2¾ × 2¾ | 5.76 |
| Norman | 11⅝ × 2¼ × 3⅝ | 4.57 |
| Utility | 11⅝ × 3⅝ × 3⅝ | 3.00 |
Concrete bag calculator
Bags for a volume:
bags = V × (1 + waste) / yield, rounded up
Yield of a bag of mass m, from 0.60 ft³ per 80 lb:
yield = m × 0.0075 ft³/lb
Common bag yields:
| Bag | Yield | Bags per yd³ | Bags per m³ |
|---|---|---|---|
| 80 lb | 0.60 ft³ (17.0 L) | 45 | 58.9 |
| 60 lb | 0.45 ft³ (12.7 L) | 60 | 78.5 |
| 50 lb | 0.375 ft³ (10.6 L) | 72 | 94.2 |
| 40 lb | 0.30 ft³ (8.5 L) | 90 | 117.7 |
| 30 kg | 0.496 ft³ (14.0 L) | 54.4 | 71.2 |
| 25 kg | 0.413 ft³ (11.7 L) | 65.3 | 85.4 |
| 20 kg | 0.331 ft³ (9.4 L) | 81.6 | 106.8 |
Concrete block calculator: CMU, mortar and grout
Blocks:
A_net = L × H − openings
blocks = A_net / (face length × face height) × (1 + waste)
Mortar and grout:
bags = blocks / 16
grout = A_net × g / 100
- L, H — wall length and height; openings — area of doors and windows
- face — nominal block face including one joint: 16 × 8 in (0.889 ft²) or 450 × 225 mm (0.101 m²)
- 16 — blocks laid per 80 lb bag of preblended mortar with face-shell bedding (NCMA TEK 4-2A Table 2)
- g — grout in ft³ per 100 ft² of wall from NCMA TEK 4-2A Table 3
Grout per 100 ft² of wall, two-core hollow units, 3 % waste included:
| Cores grouted | 6 in wall | 8 in wall | 10 in wall | 12 in wall |
|---|---|---|---|---|
| Every core | 25.6 ft³ | 36.1 ft³ | 47.0 ft³ | 58.9 ft³ |
| 16 in on centre | 12.8 ft³ | 18.1 ft³ | 23.5 ft³ | 29.5 ft³ |
| 24 in on centre | 8.6 ft³ | 12.1 ft³ | 15.7 ft³ | 19.7 ft³ |
| 32 in on centre | 6.4 ft³ | 9.1 ft³ | 11.8 ft³ | 14.8 ft³ |
| 48 in on centre | 4.3 ft³ | 6.1 ft³ | 7.9 ft³ | 9.9 ft³ |
Concrete column and post hole calculator
Round column or pier:
V = n × π × D² / 4 × H
Post hole, with the post standing on gravel:
V = n × (π × D² / 4 − A_post) × (h − h_gravel)
A_post = s² for a square post, π × s² / 4 for a round one
Order and bags:
V_order = V × (1 + waste)
bags = V_order / bag yield, rounded up
- D — hole or column diameter; H — column height; h — hole depth
- s — actual post size: a 4 × 4 is 3.5 in, a 6 × 6 is 5.5 in
- n — number of holes or columns
- bag yield — 0.60 ft³ per 80 lb, 0.45 ft³ per 60 lb, 0.30 ft³ per 40 lb, 11.7 L per 25 kg
Concrete footing calculator
Strip footing, measured along its centreline:
V = L_c × B × D
Pad footings, n of them:
V = n × L × B × D
Order volume and bags:
V_order = V × (1 + waste)
bags = V_order / bag yield, rounded up
- L_c — centreline length; for a rectangle of outside size a × b, 2 × (a + b) − 4 × B
- B — width of the footing; D — depth of concrete; L — length of one pad
- waste — 10 % is usual when pouring into an earth trench
- bag yield — 0.60 ft³ per 80 lb bag, 0.45 ft³ per 60 lb, 11.7 L per 25 kg
Concrete slab calculator
Volume of the slab and volume to order:
V = L × W × t × n
V_order = V × (1 + waste)
Unit conversions and bags:
cubic yards = cubic feet / 27
bags = V_order / bag yield, rounded up
- L, W — length and width; t — thickness, with inches divided by 12 to get feet
- n — number of identical slabs
- waste — spillage and uneven ground allowance, 5 to 10 % for slabs
- bag yield — 0.60 ft³ for 80 lb, 0.45 ft³ for 60 lb, 0.375 ft³ for 50 lb, 0.30 ft³ for 40 lb, 11.7 L for 25 kg
Concrete volume and rebar weight
Volumes:
Slab / footing: V = L × W × t, Wall: V = L × H × t
Rectangular column: V = b × d × H, Round column: V = π D² H / 4
V_net = V × count, V_order = V_net (1 + waste), m = ρ_concrete V_net
Nominal mix 1 : a : b by volume (dry-volume factor 1.54, cement bulk density 1 440 kg/m³):
dry volume = 1.54 V_order
cement volume = dry volume / (1 + a + b), cement mass = cement volume × 1 440, bags = mass / bag size
sand = a × cement volume, aggregate = b × cement volume
Reinforcement:
bar mass per metre = 7 850 × π d²/4 ≈ d² / 162 (kg/m, d in mm)
Mesh: bars along A = floor(B / s) + 1, bars along B = floor(A / s) + 1, length per layer = (bars along A) A + (bars along B) B
Bars + links: main length = n × member length; link length = (floor(member length / s_link) + 1) × [2 (a − 2c) + 2 (b − 2c) + 20 d_link]
total = (main + links) × count × (1 + lap allowance)
steel ratio = steel mass / V_net
Typical steel ratios: slabs 80–120, walls 80–150, foundations 60–150, columns 150–300 kg/m³.
Site work and building
Asphalt calculator: tons of hot mix
Volume and weight:
V = L × W × t
m = V × ρ
m_order = m × (1 + waste)
Spread rate and the US rule of thumb:
spread [lb/yd²/in] = ρ [lb/ft³] × 9 / 12
tons = yd² × inches × 110 / 2 000
- L, W — length and width of the paved area; t — compacted thickness
- ρ — compacted density of the mix in place, 145 lb/ft³ (2.32 t/m³) by default
- waste — allowance for edges, an uneven base and material left in the equipment
- 1 short ton = 2 000 lb; 1 metric tonne = 1 000 kg = 2 205 lb
The rule of 110 lb per square yard per inch matches a density of 146.7 lb/ft³. At 145 lb/ft³ the spread rate is 108.75 lb per yd² per inch.
Earthwork cut and fill volumes
V_AEA = L (A₁ + A₂)/2
V_prismoidal = L (A₁ + 4 A_m + A₂)/6, A_m measured or ≈ ((√A₁ + √A₂)/2)² for similar sections
correction = V_AEA − V_prismoidal
cut: V_bank = V, V_loose = V_bank (1 + swell), V_compacted = V_bank (1 − shrinkage)
fill: V_compacted = V, V_bank = V/(1 − shrinkage), V_loose = V_bank (1 + swell)
mass = V_bank ρ_bank, ρ_loose = ρ_bank/(1 + swell), loads = V_loose / truck capacity
Typical factors: sand and gravel swell 12 % / shrinkage 12 %; loam 25 % / 10 %; clay 33 % / 10 %; topsoil 25 % / 15 %; blasted rock swell 50 % and bulking 30 % when placed.
Gravel calculator: cubic yards and tons
Volume in place and volume to order:
V = L × W × d
V_order = V × (1 + c)
Weight, truck loads and cost:
m = V_order × ρ
loads = larger of V_order / truck volume and m / truck payload, rounded up
cost = tons × price per ton
- L, W — length and width of the area; d — compacted depth, with inches divided by 12 to get feet
- c — compaction and settlement allowance, as a fraction
- ρ — loose bulk density of the delivered material
- 1 yd³ = 27 ft³ = 0.7646 m³; 1 short ton = 2 000 lb = 907.2 kg
Loose bulk densities from the Caterpillar Performance Handbook:
| Material | kg/m³ | lb/yd³ | short tons per yd³ |
|---|---|---|---|
| Crushed stone | 1 600 | 2 700 | 1.35 |
| Gravel, dry, ¼ to 2 in | 1 690 | 2 850 | 1.43 |
| Sand and gravel, dry | 1 720 | 2 900 | 1.45 |
| Sand, dry | 1 420 | 2 400 | 1.20 |
| Topsoil | 950 | 1 600 | 0.80 |
Roof pitch calculator: rafters, area and shingles
Pitch, angle and multiplier:
s = pitch / 12 = tan θ
k = √(1 + s²)
Gable roof:
rafter = (span / 2 + eave overhang) × k
ridge height = (span / 2) × s
area = (span + 2 × eave) × (length + 2 × rake) × k
squares = area × (1 + waste) / 100 ft²
bundles = squares × 3, rounded up
- pitch — rise in inches per 12 in of run; θ — roof angle; s — slope as a fraction
- span — building width from wall to wall; length — along the ridge
- eave, rake — horizontal overhangs at the eaves and at the gable ends
- k — pitch multiplier, slope length per unit of horizontal run
| Pitch | Angle | Multiplier |
|---|---|---|
| 4/12 | 18.4° | 1.054 |
| 6/12 | 26.6° | 1.118 |
| 8/12 | 33.7° | 1.202 |
| 12/12 | 45.0° | 1.414 |
Slope calculator: percent, degrees, ratio and pitch
From rise and run:
grade = rise / run percent = 100 × rise / run
θ = arctan(rise / run)
ratio 1 : n, n = run / rise
pitch = 12 × rise / run inches per foot
length along the slope = √(run² + rise²)
- rise — vertical change; run — horizontal distance
- θ — angle above the horizontal
Stair calculator: risers, treads and stringer
Risers, treads and run:
n = H / R_max, rounded up
R = H / n
treads = n − 1
run = treads × T
Stringer, angle and comfort:
stringer = √(H² + run²)
θ = atan(R / T)
comfort = 2R + T
- H — total rise from finished floor to finished floor
- R_max — the tallest riser you allow; R — the actual, equal riser height
- T — tread depth, nosing to nosing
- n — number of risers; the top riser lands on the upper floor, so there is one tread fewer
Code limits checked:
| Item | IRC R311.7 (dwellings) | IBC §1011 (other buildings) |
|---|---|---|
| Riser height | 7¾ in maximum | 4 to 7 in |
| Tread depth | 10 in minimum | 11 in minimum |
| Headroom | 6 ft 8 in | 80 in |
| Rise of one flight | 151 in | 12 ft |
Trench and excavation volume calculator
Trench cross-section with side slopes n H : 1 V, and volumes:
A = (b + n d) × d
V_bank = A × L
V_loose = V_bank × (1 + swell)
loads = V_loose / truck capacity, rounded up
V_backfill = V_bank − π D² L / 4
- b — bottom width; d — depth; L — length; n — horizontal run per unit of depth
- OSHA maximum slopes: stable rock vertical, Type A ¾ : 1, Type B 1 : 1, Type C 1½ : 1
- D — outside diameter of the pipe laid in the trench
Foundations and soils
Consolidation settlement calculator (clay layer)
Settlement, with σ'1 = σ'0 + Δσ:
normally consolidated: S = Cc H/(1 + e0) log(σ'1/σ'0)
over-consolidated, σ'1 ≤ σ'p: S = Cr H/(1 + e0) log(σ'1/σ'0)
over-consolidated, σ'1 > σ'p: S = Cr H/(1 + e0) log(σ'p/σ'0) + Cc H/(1 + e0) log(σ'1/σ'p)
Rate of consolidation (Terzaghi):
T_v = c_v t / H_dr²
U = 1 − Σ (2/M²) exp(−M² T_v), M = π(2m + 1)/2, m = 0, 1, 2 …
T_v ≈ (π/4) U² for U ≤ 60 %; T_v ≈ 1.781 − 0.933 log(100 − U%) for U > 60 %
- H — layer thickness; e0 — initial void ratio; Cc, Cr — compression and recompression indices
- σ'0 — present effective stress at mid-layer; σ'p — preconsolidation pressure; Δσ — stress increase
- c_v — coefficient of consolidation; H_dr — drainage path, H/2 when both faces drain
Crane outrigger pad bearing pressure
F = manufacturer value, or ≈ 0.65 × (crane + load + rigging) g, or (crane + load + rigging) g
q_float = F / A_float
rigid mat: q = (F + W_mat) / (L_mat B_mat), bending σ = 3 q c² / t², c = largest overhang beyond the float
spread: L_eff = min(L_mat, L_float + 2 t tan θ), q = F / (L_eff B_eff) + W_mat / A_mat
required area = F / q_allow, square side = √(F / q_allow)
BS 8004 presumed allowable values (lower bounds): rock 4 000, dense gravel 600, compact sand 300, very stiff clay 300, medium dense gravel 200, stiff clay 150, medium dense sand 100, firm clay 75 kPa; soft or loose ground must be tested.
Footing size calculator
Net allowable pressure and required area:
q_net = q_all − γ_c t − γ_s h_s
A = P / q_net
Plan dimensions:
square: B = √A
round: D = √(4A / π)
rectangle: B = √(A / r), L = r B
strip: B = w / q_net
Actual pressure with the rounded size:
q = P / A_rounded + γ_c t + γ_s h_s
- P — service (unfactored) column load; w — load per length of wall
- q_all — allowable bearing pressure; t — footing thickness; h_s — soil above the footing
- γ_c, γ_s — unit weights of concrete and soil; r — length to width ratio
Pile capacity calculator (driven and bored piles)
Ultimate and allowable capacity:
Q_ult = Q_s + Q_b = Σ f_i P Δz_i + q_b A_b
Q_all = Q_ult / FS
Driven piles (API RP 2GEO):
clay: f = α s_u, α = 0.5 ψ^−0.5 (ψ ≤ 1) or 0.5 ψ^−0.25 (ψ > 1), α ≤ 1, ψ = s_u / σ'v
q_b = 9 s_u
sand: f = β σ'v ≤ f_lim, q_b = N_q σ'v ≤ q_lim (dense sand: β 0.46, 96 kPa, N_q 40, 10 MPa)
Bored piles (O'Neill and Reese, FHWA 1999):
clay: f = 0.55 s_u, none in the top 1.5 m and the bottom D; q_b = 6 (1 + 0.2 L/D) s_u ≤ 9 s_u
sand: f = β σ'v ≤ 200 kPa, β = 1.5 − 0.245 √z (0.25 to 1.2, z in m); q_b = 57.5 N60 kPa
- P — pile perimeter; A_b — base area; D — diameter; L — embedded length
- s_u — undrained shear strength; σ'v — effective vertical stress; N60 — SPT blow count
Retaining wall earth pressure calculator (Rankine)
Earth pressure coefficients:
K_a = tan²(45° − φ/2) active, level backfill
K_a = cos β (cos β − √(cos²β − cos²φ)) / (cos β + √(cos²β − cos²φ)) sloping backfill
K_p = tan²(45° + φ/2) passive
K_0 = 1 − sin φ at rest (Jaky)
Thrust per metre of wall and its height above the base:
P = ½ K γ H² + K q H
ȳ = ( ½ K γ H² × H/3 + K q H × H/2 ) / P
Gravity wall of width b and weight W = γ_w b H:
FS_sliding = μ W / P_h, FS_overturning = (W b / 2) / (P_h ȳ)
- φ — friction angle of the backfill; γ — its unit weight; H — retained height
- q — uniform surcharge; β — slope of the backfill; μ — friction between base and soil
Soil bearing capacity calculator (Terzaghi and Eurocode 7)
General form, for a footing of width B at depth D_f:
q_ult = c N_c s_c + q N_q s_q + ½ γ B N_γ s_γ, q = γ D_f
Eurocode 7 Annex D factors (drained):
N_q = e^{π tan φ} tan²(45° + φ/2)
N_c = (N_q − 1) cot φ, N_γ = 2 (N_q − 1) tan φ
s_q = 1 + (B/L) sin φ, s_γ = 1 − 0.3 B/L, s_c = (s_q N_q − 1)/(N_q − 1)
Undrained (clay, short term):
q_ult = (π + 2) c_u (1 + 0.2 B/L) + q
Terzaghi:
N_q = e^{2(3π/4 − φ/2) tan φ} / (2 cos²(45° + φ/2)), N_c = (N_q − 1) cot φ
square: 1.3 c N_c + q N_q + 0.4 γ B N_γ; circle: 1.3 c N_c + q N_q + 0.3 γ B N_γ
- φ — friction angle; c — cohesion; c_u — undrained shear strength; γ — unit weight of the soil
- Allowable pressure: q_all = q_ult / FS, with FS usually 2.5 to 3
Soil compaction calculator (Proctor relative compaction)
Dry density and relative compaction:
ρ_d = ρ / (1 + w)
RC = ρ_d / ρ_d,max × 100 %
Weight–volume relations:
e = G_s ρ_w / ρ_d − 1, n = e / (1 + e)
S = w G_s / e
V_a = 1 − (ρ_d / ρ_w)(1/G_s + w)
Zero-air-voids density, the upper limit at moisture w:
ρ_zav = G_s ρ_w / (1 + w G_s)
- ρ — wet (bulk) density; w — moisture content as a decimal
- ρ_d,max — maximum dry density from the Proctor test
- G_s — specific gravity of the soil solids; ρ_w = 1 000 kg/m³ = 62.43 lb/ft³
Surveying and roads
Closed traverse calculator (compass rule)
Latitude and departure of each leg, with the azimuth Az measured clockwise from north:
Lat = L × cos Az, Dep = L × sin Az
Misclosure and precision:
e = √( (ΣLat)² + (ΣDep)² )
precision = 1 : (ΣL / e)
Compass (Bowditch) rule corrections for leg i:
C_lat,i = −ΣLat × L_i / ΣL, C_dep,i = −ΣDep × L_i / ΣL
N_i+1 = N_i + Lat_i + C_lat,i, E_i+1 = E_i + Dep_i + C_dep,i
- L — horizontal length of a leg; ΣL — total length of the traverse
- A bearing such as S 75°30′ E is the azimuth 180° − 75°30′ = 104°30′
- The area of the adjusted polygon comes from the coordinate (shoelace) formula
Latitude/longitude to UTM converter (WGS84)
Ellipsoid and series constants (WGS84, a = 6 378 137 m, f = 1/298.257223563):
n = f / (2 − f), e² = f (2 − f)
A = a / (1 + n) × (1 + n²/4 + n⁴/64 + n⁶/256)
Forward, with λ the longitude from the zone's central meridian:
τ = tan φ, σ = sinh(e atanh(e τ / √(1 + τ²)))
τ′ = τ √(1 + σ²) − σ √(1 + τ²)
ξ′ = atan2(τ′, cos λ), η′ = asinh(sin λ / √(τ′² + cos² λ))
ξ = ξ′ + Σ α_j sin(2jξ′) cosh(2jη′), η = η′ + Σ α_j cos(2jξ′) sinh(2jη′)
E = 500 000 + k₀ A η, N = k₀ A ξ (+ 10 000 000 south of the equator)
Inverse: the same series with the β_j coefficients, then φ from τ′ by Newton's method.
- φ — latitude; λ — longitude difference; k₀ = 0.9996 — scale on the central meridian
- α_j, β_j — Krüger coefficients, polynomials in n up to n⁶ (Karney 2011)
- Zone = floor((longitude + 180°) / 6°) + 1, with the Norway and Svalbard exceptions
Polygon area from coordinates (shoelace method)
Shoelace (Gauss) formula for n corners, with corner n + 1 equal to corner 1:
2A = Σ (x_i y_i+1 − x_i+1 y_i)
A = |2A| / 2
Perimeter and centroid:
P = Σ √( (x_i+1 − x_i)² + (y_i+1 − y_i)² )
C_x = Σ (x_i + x_i+1)(x_i y_i+1 − x_i+1 y_i) / (6 A_signed)
C_y = Σ (y_i + y_i+1)(x_i y_i+1 − x_i+1 y_i) / (6 A_signed)
- x, y — easting and northing of each corner, in order round the boundary
- A positive sum means counter-clockwise corners, a negative one clockwise
- 1 acre = 43 560 ft² = 4 046.856 m²; 1 hectare = 10 000 m²
Vertical curve calculator (crest and sag)
Elevation at a distance x from the PVC on a curve of length L:
y = y_PVC + g1 x + (g2 − g1) x² / (2L)
y_PVC = y_PVI − g1 L/2, y_PVT = y_PVI + g2 L/2
High or low point and the K value:
x_turn = −g1 L / (g2 − g1)
A = |g2 − g1| in %, K = L / A
AASHTO sight distance S provided, in feet (metric constants in brackets):
crest, S < L: L = A S² / 2158 [658] S > L: L = 2S − 2158/A [658]
sag, S < L: L = A S² / (400 + 3.5 S) [120 + 3.5 S]
stopping sight distance needed = 1.47 V t + 1.075 V²/a, t = 2.5 s, a = 11.2 ft/s²
- g1, g2 — grades in and out, as decimals in the elevation formula
- Stations increase in the direction of travel; 25+60 means 2 560 ft
- V — design speed in mph; the metric form is 0.278 V t + 0.039 V²/a with V in km/h and a = 3.4 m/s²
Drainage and hydraulics
Culvert capacity and headwater calculator (HDS-5)
Inlet control, HDS-5 Appendix A, with D in ft and Q in ft³/s:
unsubmerged (Q/AD^0.5 ≤ 3.5): HW/D = Hc/D + K (Q / A D^0.5)^M − 0.5 S
submerged (Q/AD^0.5 ≥ 4.0): HW/D = c (Q / A D^0.5)² + Y − 0.5 S
Outlet control with the barrel flowing full, HDS-5 chapter 3:
H = [1 + ke + 29 n² L / R^1.33] × V² / 2g
HW = H + h_o − L S, h_o = max(TW, (d_c + D) / 2)
- D — pipe diameter or box rise; A — full barrel area; S — barrel slope
- Hc — specific head at critical depth, d_c + V_c²/2g; between 3.5 and 4.0 the result is interpolated
- K, M, c, Y — inlet constants of HDS-5 Table A.1; ke — entrance loss coefficient of Table C.2
- n — Manning roughness; L — barrel length; R — hydraulic radius; V = Q / A
- TW — tailwater depth above the outlet invert; d_c — critical depth
| Inlet | K | M | c | Y | ke |
|---|---|---|---|---|---|
| Pipe, square edge with headwall | 0.0098 | 2.0 | 0.0398 | 0.67 | 0.5 |
| Pipe, groove end with headwall | 0.0018 | 2.0 | 0.0292 | 0.74 | 0.2 |
| Pipe, groove end projecting | 0.0045 | 2.0 | 0.0317 | 0.69 | 0.2 |
| Box, wingwalls 30° to 75° | 0.026 | 1.0 | 0.0347 | 0.81 | 0.4 |
| Box, wingwalls 90° or 15° | 0.061 | 0.75 | 0.0400 | 0.80 | 0.5 |
| Box, wingwalls 0° | 0.061 | 0.75 | 0.0423 | 0.82 | 0.7 |
Drain pipe size calculator (Manning)
Manning's equation for a pipe flowing full:
V = (1/n) × R^(2/3) × S^(1/2) (SI, metres)
V = (1.486/n) × R^(2/3) × S^(1/2) (US, feet)
Q = A × V, A = π D² / 4, R = D / 4
Part-full pipe at depth y, and the minimum slope:
θ = 2 acos(1 − 2y/D)
A = D² (θ − sin θ) / 8, P = D θ / 2, R = A / P
S_min = (n × V_min / R^(2/3))²
- D — inside diameter; S — slope as a fraction, 1 % = 0.01
- n — Manning roughness: 0.009 for smooth PVC, 0.013 for concrete and clay, and for any pipe where the agency requires it
- V_min — self-cleansing velocity, 2.0 ft/s (0.61 m/s) flowing full
- A, P, R — flow area, wetted perimeter and hydraulic radius
Open-channel flow (Manning)
Section geometry (depth y):
Rectangular: A = b y, P = b + 2y, T = b
Trapezoidal: A = (b + z y) y, P = b + 2y √(1 + z²), T = b + 2 z y
Triangular: A = z y², P = 2y √(1 + z²), T = 2 z y
Circular: θ = 2 acos(1 − 2y/D), A = D² (θ − sin θ)/8, P = D θ/2, T = D sin(θ/2)
R = A / P
Manning (SI):
V = (1/n) R^(2/3) S^(1/2), Q = A V
Normal depth: the y for which A V = Q (bisection). Circular pipes carry their maximum free-surface discharge at about 94 % depth; above that the capacity falls back to the full-pipe value.
Critical flow and energy:
Fr = V / √(g A/T) (< 1 subcritical, > 1 supercritical)
critical depth y_c: Q² T / (g A³) = 1 (rectangle: y_c = (q²/g)^(1/3), q = Q/b)
E = y + V² / (2g)
τ₀ = ρ g R S
Manning n (Chow, normal values): PVC 0.009; coated steel 0.012; finished concrete 0.013; rough concrete 0.017; corrugated metal 0.024; clean earth 0.022; weedy earth 0.030; gravel 0.025; riprap 0.035; natural clean stream 0.030; weedy stream 0.050.
Rational-method runoff
C = Σ C_k A_k / Σ A_k composite runoff coefficient
t_c = 0.0195 L^0.77 S^−0.385 [min] Kirpich (L m, S m/m); design duration = max(t_c, minimum)
i = a / (t_c + b)^n optional IDF fit (mm/h), else the IDF-curve value at t_c
Q = C C_f i A / 360 [m³/s] i mm/h, A ha, C C_f ≤ 1
depth = C C_f i t_c, volume = depth × A
Runoff coefficients (2–10 year storms): roofs 0.90, pavement 0.85, industrial 0.75, gravel 0.50, residential 0.40, lawns 0.10–0.30, woodland 0.15. Frequency factor C_f: 1.0 up to 10 years, 1.1 (25), 1.2 (50), 1.25 (100).
Weir and flume flow calculator
Sharp-crested weirs, head H and crest length L in feet, flow in ft³/s:
rectangular (Francis): Q = 3.33 (L − 0.1 n H) H^1.5
90° V-notch (Cone): Q = 2.49 H^2.48
Cipolletti: Q = 3.367 L H^1.5
Parshall flume, upstream head H_a in feet:
Q = C × H_a^n (1 in to 1 ft, USBR Table 8-6)
Q = 4 W × H_a^(1.522 W^0.026) (2 to 8 ft)
- n — number of end contractions: 2 for a notch narrower than the channel, 0 for a suppressed weir across the full width
- W — throat width of the flume in feet
- C, n — 0.338 and 1.55 for 1 in; 0.676 and 1.55 for 2 in; 0.992 and 1.55 for 3 in; 2.06 and 1.58 for 6 in; 3.07 and 1.53 for 9 in; 3.95 and 1.55 for 1 ft
- metric inputs are converted to feet; 1 ft³/s = 28.32 L/s = 448.8 US gpm
Results are estimates. They do not replace the governing code, class or flag requirements, or a check by a competent person.